    November 17, 2026

    On October 15, a unanimous Mississippi Supreme Court held in Cuevas Machine Co. v. Calgon Carbon Corp. that dated invoices attached to a construction lien do not satisfy Mississippi Code Section 85-7-405(1)(b) unless they plainly identify the last date work was performed.  This is the first time the court has interpreted this statutory lien requirement and opined on what constitutes identifying the last date of work.  Omitting this date renders an entire lien invalid and potentially subjects the lienor to treble damage penalties.

    Cuevas, a subcontractor, filed two liens totaling more than $1.2 million that omitted the date the claim was due but attached dated invoices. After the federal district court dismissed Cuevas' complaint with prejudice, the Fifth Circuit certified the question to the court.

    The court noted that it has never decided whether a lien's required contents may be supplied by attachments and did not decide that question here. Instead, it accepted the Fifth Circuit's framing and assumed that attachments could supply the date. Even under that assumption, the attachments must clearly specify the date the claim was due, which is the last date labor, services, or materials were supplied. That date matters because it starts the 90-day filing deadline. Without it, the owner lacks adequate notice, and no one can readily tell whether the lien was timely.

    Cuevas's invoices fell short. One lien attached eleven invoices bearing seven different dates, and the other attached eight invoices all dated September 6, 2023. Nothing showed whether those dates reflected when services were performed, when the invoices were generated, or something else. The court rejected Cuevas's "substantial compliance" argument. It explained that the statute's "in substance" language refers to the sample lien form and does not override the separate requirement to specify the date.

    Distinguishing Land Holdings I, LLC v. GSI Services, LLC, where the lien stated a date and the only dispute was its accuracy, and following its strict reading of the same statute in KD Oak Grove, LLC v. Warren & Warren Asphalt Paving, LLC, the court concluded that "[s]imply including a dated attachment such as an invoice, with no explanation as to what the date represents is insufficient."

    Key Takeaways

    When drafting a construction lien, it is important to have clear records of when and how labor, services, or materials were supplied to a project.  With those records, a lienor can state with confidence the last date labor, services, or materials were supplied expressly in the body of the lien, rather than relying on scattered invoices or a host of attachments to supply it.  Similarly, when defending against a lien action, attention to the actual dates provided are crucial for contesting the validity of the lien.

    Please contact John McMackin, Adam Harris or any member of the Construction/Design team if you have questions or need advice or guidance.

    Related Professionals

    -
    John P. McMackin John McMackin photograph

    John P. McMackin

    Email

    Adam B. Harris

    Adam B. Harris

    Email

    Related Practices

    • Construction/Design
    Stay connectedReceive our latest thinking on topics you care about.SIGN UP NOW
    • ©2026 Phelps Dunbar LLP. All Rights Reserved
    • Lawyer Advertising
    • Privacy & Disclaimer
    • Contact Us
    © 2026 Phelps Dunbar LLP. All Rights Reserved